Giles and Paula Add a Room Onto the Side of The House
-
Progress is coming along nicely.
-
I think it looks GREAT….
-
Definitely enjoy seeing the progress
-
I've decided to slow things down a bit. Things are going really well, but I made a cock up with my floor height calcs. so I need to add some more screed else finished floor level will be below DPC. I don't think it will make a blind bit of difference to the functionality of the building, but it's outside of building regs. It'll never be noticed, but I may as well do it right. I need to wait for the current screed to dry naturally (about another 30 days) or put the underfloor heating on to accelerate the drying time. But that means I have to screw up our current kitchen earlier than I wanted too, so on balance, a slow down is more sensible.
-
There might be a risk the underfloor heating could dry the screed too quickly?….cracking??
-
how thick (in cm) is the screed? @Giles …normally the rule is 1cm screed needs one week to try (without any kinda accelerator that is!).
about drying the screed with turned on underfloor heating, the way to do it is sth. like the following:
25c - day 1-3
30c - day 4-6
35c - day 7-9
40c - day 10-12
45c - day 13-16
40c - day 17-20for info, if the screed is bound with calcium sulfit, you‘re not allowed to heat it up more than 50c!
-
Looking forward to seeing how the doors turn out!